Malmberget, 25 August 2026: LKAB is building a new sorting plant at its Malmberget mine in Gällivare, a SEK 6 billion investment that its board approved in September 2025. The plant is due to start operating in 2028, the company said in a press release.
It is designed for 25 million tonnes of crude ore a year, about 7 to 8 million tonnes more than the current capacity. The building has a volume of 620,000 cubic metres, and the facility it replaces was commissioned in 1953. NCC is the main contractor.
LKAB says the plant should bring more stable and efficient production, with fewer disruptions and a better working environment for employees. As outdoor operations are phased out, the company also lists lower noise, dust and CO2 emissions among the benefits.
A link to rare earths in Luleå
The plant is also being prepared to handle apatite-rich tailings, for the future extraction of apatite that LKAB plans to use in its production of phosphorus and rare earth elements in Luleå.
The permits behind that chain moved forward in the second quarter. In its interim report for April to June 2026, published on 13 August, LKAB said the Land and Environment Court granted two permits: one for its planned industrial park in Luleå for extracting critical minerals, and one for Malmberget, which includes an apatite plant that will supply the Luleå park with apatite concentrate. According to the report, the Gällivare process continues at the next level of review after appeals were filed.