Arverne’s Lithium de France runs both Schwabwiller geothermal wells together for the first time

A geothermal power plant on a hillside at Soultz-sous-Forêts, Alsace

On 20 August 2026, Lithium de France began operating the two wells of its geothermal doublet at Schwabwiller, in the commune of Betschdorf (Bas-Rhin), at the same time, according to the company. The project, a subsidiary of the Arverne group, aims to produce heat and lithium from the same geothermal water.

Two wells, one loop

Drilling of the first well started on 24 November 2025, the company announced that day. The doublet consists of one production well, which brings up the hot water, and one injection well, which returns it to the reservoir. According to Arverne’s 24 November 2025 announcement, the wells were designed to be 10 metres apart at the surface and to diverge underground, to reach about one kilometre of separation at a depth of 2,400 metres.

Drilling is supervised by the teams of Lithium de France and Arverne, which describes itself as heir to 60 years of drilling expertise. The two wells were tested separately, in March and July 2026, before the joint test.

A circulation test with a lithium demonstrator

The joint test, described by Lithium de France in a post of 3 September 2026, was planned to last three to four weeks, in a continuous open-loop circulation, and was scheduled to end on 18 September 2026. Once flows have stabilised, a tracer is to be injected to measure how fast water travels between the two wells. A direct lithium extraction demonstrator is connected to the production flow to assess performance under real conditions.

The company monitors the site with its own network of seismic stations, following BRGM and Ineris good-practice guidelines under DREAL supervision. In addition, Lithium de France has launched a scientific partnership with the Karlsruhe Institute of Technology (KIT) on induced seismicity in the Upper Rhine Graben, combining seismological sensors and optical fibre at the Schwabwiller site, supported by the GFZ Helmholtz Centre for Geosciences. The company says the tests, like any operation of this type, may be accompanied by induced microseismicity, generally imperceptible at the surface.

Permits and a resource estimate

Schwabwiller is the project’s first operating site. It sits on two exclusive research permits covering 171 km²: "Les Sources" for geothermal heat, granted on 22 June 2022, and "Les Sources Alcalines" for geothermal lithium, granted on 24 July 2023. An environmental authorisation was issued on 16 May 2025, according to Arverne.

Arverne said on 14 September 2026 that Sproule ERCE, under the NI 43-101 standard, estimated indicated and inferred resources at 26 million tonnes of lithium carbonate equivalent and a total exploration potential of up to 43 million tonnes across four permits, two of which (Plaine du Rhin and Les Coteaux minéraux) are still under review. The evaluation followed a 3D seismic campaign and the two first wells at Schwabwiller.

The next permits are open to public comment

2gré, a subsidiary of Arverne, has applied to extend its "Strasbourg" geothermal permit and to obtain a new "Plaine du Rhin" lithium permit. A public consultation on both runs from 7 to 28 September 2026, according to Arverne. The Géothermies website of ADEME and BRGM gives areas of about 573 km² for the Strasbourg permit and 554 km² for Plaine du Rhin, the latter lying entirely within the former.

Financing and jobs

On 26 May 2026, Arverne and its partner Equinor Ventures announced a convertible bond of up to €33 million for Lithium de France, maturing on 30 June 2027. It converts if the company secures €50 million of qualifying financing, in debt, subsidies or equity. The funds cover the pre-industrial phase: drilling, the lithium extraction demonstrator and front-end engineering studies. Equinor Ventures has been a shareholder since 2021.

Lithium de France targets 27,000 tonnes of lithium carbonate a year and 2.2 TWh of geothermal heat for businesses, farmers and communities in northern Alsace. The company puts the expected direct employment at nearly 200 jobs in the region.