London and Berlin held offshore wind auctions within six months of each other with different outcomes, under different designs: a contract-for-difference round in the UK and, in Germany, a sealed-bid auction without EEG subsidies. On 14 January 2026 the UK’s Department for Energy Security and Net Zero announced that its seventh allocation round had secured 8.4 GW, which it described as Europe’s biggest ever offshore wind auction. On 6 August 2025 the German energy industry association BDEW reported that the Bundesnetzagentur had received no bids for two North Sea sites totalling 2,500 MW, the first time a German offshore wind tender round drew no bids, according to the BDEW.
The UK secured its capacity at an average of £90.91 per megawatt hour for fixed-bottom wind, in 2024 prices, and £216.46 for floating wind. In 2012 prices, the government says, the fixed-bottom price is £65.25. It puts the private investment unlocked at around £22 billion, the jobs supported at around 7,000, and the electricity at the equivalent of 12 million homes. Winning projects include Dogger Bank South, Norfolk Vanguard, Berwick Bank, Awel Y Môr, Erebus and Pentland. Energy Secretary Ed Miliband called the result "a historic win for those who want Britain to stand on our own two feet".
In Germany, sites N-10.1 (2,000 MW) and N-10.2 (500 MW) drew no offers, in a sealed-bid auction held without EEG subsidies. Their planned commissioning dates were the third quarter of 2031 and the fourth quarter of 2030. The BDEW, Germany’s energy and water industry association, named three causes: higher project and capital costs linked to geopolitical tensions and supply chain bottlenecks, unpredictable electricity price and volume risks, and much lower full-load hours caused by wake effects from dense turbine spacing. Kerstin Andreae of the BDEW said that the risks for offshore developers have "increased considerably in recent years" (translated from German).
The BDEW called for a reform of the Offshore Wind Act (WindSeeG), a switch from power purchase agreements to bilateral contracts for difference, and a power density below 10 MW per square kilometre. The two sites were to be re-tendered as sites not pre-surveyed by the state, with a bid date of 1 June 2026. According to the Bundesnetzagentur, however, the 2026 offshore auctions were moved to auction year 2027 by the amendment of the 2025 area development plan of 30 January 2026, and N-10.1 and N-10.2 are among the six sites affected.
Image credit: Andy Dingley (edit: Muhammad), CC BY-SA 3.0, Wikimedia Commons (https://commons.wikimedia.org/wiki/File:Barrow_Offshore_wind_turbines_NR.jpg)