France’s Commission de régulation de l’énergie (CRE) approved on 10 September 2026 the procedure through which the grid operator RTE will connect the offshore wind farms of the "PPE3" group of projects in its tenth offshore wind tender, known as AO10. The regulator published the decision on 16 September. Bids for the tender, which covers eleven projects and about 10 gigawatts (GW), are due by noon on 12 October 2026.
What the regulator approved
The CRE approved what it describes as a simplified specific procedure for offshore wind connection, together with the model connection agreement, for the group of projects it calls "PPE3" within AO10. The projects named are Fécamp Grand Large 1 to 3, Bretagne Nord-Ouest, Oléron 1, and Golfe du Lion Centre 1a, 1b and 2. The tender itself covers eleven projects; the CRE’s decision names these eight as the PPE3 group. The procedure is built around three stages of progressive commitment between RTE and the producer, with what the CRE calls an evolving liability cap.
RTE submitted its proposal to the CRE on 22 July 2026. A public consultation on the procedure ran from 10 March to 7 April 2026, and the government published the tender specifications on 12 June 2026.
The tender the procedure serves
The French economy ministry announced the AO10 specifications on 12 June 2026. The tender puts about 10 GW into competition on eleven projects spread across the waters off Normandy, Brittany, the south Atlantic and the Mediterranean: about 5 GW of fixed-bottom and 5 GW of floating wind. Site capacities range from 0.5 GW to 1.35 GW per project; Fécamp Grand Large, at three times 1.35 GW (4.05 GW in total), is the largest. The ministry states a target weighted average price below €100 per megawatt hour.
The CRE’s page for the tender shows the bid phase as open. Candidates submit one file per project through an online platform, and the specifications were updated in a rectified version on 20 August 2026. According to the ministry, the CRE will analyse the bids and give its opinion in early 2027, and the minister is scheduled to award the projects in February 2027.
The European supply-chain criteria
The ministry says the specifications include, for the first time in a French offshore wind tender, eligibility and scoring criteria on supply chain resilience derived from the EU’s Net Zero Industry Act. It places AO10 within national targets of 15 GW of offshore wind installed by 2035 and 45 GW by 2050, the latter covering nearly 20 per cent of French electricity needs.
Image credit: Benjamin Simon (Ifremer), CC BY 4.0, Wikimedia Commons (https://commons.wikimedia.org/wiki/File:Eoliennes_du_parc_de_Fécamp_lors_de_la_mission_EMOI_(Ifremer_01076-118787_-_506737).jpg)